Here’s the ERC Order (pdf) on setting for Hearing a petition for Early Open Access. It includes, at least in part, the petition.
The petitioners include:
- PIPPA
- Meralco
- VECO
- Davao Light
- Cepalco
- San Fernando EL&P
- PECO
The petitioners are asking for Interim Open Access (i.e. not according to EPIRA) in Luzon and Visayas (only, i.e. not in Mindanao), implemented according a Terms of Reference (ToR) they have all agreed to.
Some components of the ToR include (condensed version):
- Eligible customers are initially those with 1 MW of load
- Six months later, the threshold is reduced to 750 kW
- Eligible generators are essentially any generator, except NPC and it’s IPPs
- NPC can participate once the EPIRA thresholds have been met (essentially, 70% privatized)
- All TSCs stay in place for their full term, except for adjustments for load lost to a privatized NPC generator
Jurisdictional and Pre-Trial (for Luzon) set for June 16, with Evidentiary Hearing June 17.